The Process

From first sketch
to first swim.

A high-quality pool from day one, built in the open — usually three to six weeks through engineering and permits, then eight to twelve weeks of construction, depending on city, scope, and weather.

1980Family-built since
300+Custom pools built
5.0On Google & Yelp
#636145Licensed CSLB
The build, week by week

Eight phases. No surprises.

Plenty of builders start you with the cheapest pool they can pour, then upsell from there. We do the opposite — we start you with the best equipment and materials we have (premium Pentair gear, highway-grade concrete, a dedicated project manager who's never a sales rep) and walk you through every phase below. Timelines flex with scope, your city or county, and weather.

The photos with each phase are from several of our recent builds, not one single pool. Tap any photo to see it larger.

Where every project starts

Design in 3D

We design your pool in an interactive 3D walk-through with hyper-realistic photo renders on your actual lot, refining every detail with you until it's exactly right. What you approve in 3D is what we build.

You see it in 3D before we engineer or dig
3D design render of a geometric pool with turf-strip decking, made before engineering or digging
3D design render of a geometric pool with turf-strip decking, made before engineering or digging
Before we break ground · ~3–6 weeks

Permits, engineering & your layout

We handle engineering and submit for permits — usually three to six weeks, depending on your city or county. Some HOAs require their sign-off before permits can even be submitted, so we get that moving early. Then we lay the pool out in your yard and you walk it, approving the shape and placement before a shovel touches dirt.

You approve the layout before we dig
Construction drawing for a pool and raised spa: specs, equipment, plumbing, gas and electrical runs, and setbacks, ready for engineering and permits
Construction drawing for a pool and raised spa: specs, equipment, plumbing, gas and electrical runs, and setbacks, ready for engineering and permits
Week 1

Excavation

We dig. The shape you signed off on starts taking form in the ground.

Freshly dug geometric pool with wood forms and string lines marking the shape
Freshly dug geometric pool with wood forms and string lines marking the shape
Weeks 2–3

Plumbing, steel & first inspection

Rough plumbing and electrical go in and the steel rebar shell is framed (spa plumbing follows the steel). Then the city signs off at the pre-gunite inspection before anything gets covered.

Steel rebar cage framed for a freeform pool and attached spa
Steel rebar cage framed for a freeform pool and attached spa
Steel rebar grid framed in an excavated geometric pool, ready for gunite
Steel rebar grid framed in an excavated geometric pool, ready for gunite
Spa jet and return plumbing wrapped and set inside the steel cage
Spa jet and return plumbing wrapped and set inside the steel cage
Plumbing lines, gas and electrical conduit run together in the equipment trench
Plumbing lines, gas and electrical conduit run together in the equipment trench
Pressure gauge on the new plumbing during a pressure test
Pressure gauge on the new plumbing during a pressure test
Weeks 3–4

Gunite & tile

Gunite forms the structural shell of the pool. Tile goes in next — have your selections made before gunite, and you're encouraged to inspect the tile at install.

Pick tile before gunite · inspect at install
Crew shooting and finishing the gunite shell of a pool and raised spa
Crew shooting and finishing the gunite shell of a pool and raised spa
Finished gunite shell with wide steps, a bench and the spa wall
Finished gunite shell with wide steps, a bench and the spa wall
White tile going on a raised spa above the gunite shell
White tile going on a raised spa above the gunite shell
Spa with tile on the bond beam and jet fittings ready for plaster
Spa with tile on the bond beam and jet fittings ready for plaster
Weeks 5–7

Decking

Concrete is set and the pre-deck inspection clears, then we pour your deck — six-sack, highway-grade concrete with fiber mesh in the mix and rebar throughout, over a crushed-rock base.

Crushed-rock base graded around the pool with rebar staged for the deck
Crushed-rock base graded around the pool with rebar staged for the deck
Rebar grid laid over the crushed-rock base around a freeform pool and spa
Rebar grid laid over the crushed-rock base around a freeform pool and spa
Freshly poured concrete deck panels in wood forms around the pool and spa
Freshly poured concrete deck panels in wood forms around the pool and spa
Weeks 8–9

Equipment set & safety check

Your Pentair equipment is installed and dialed in. At the pre-plaster inspection you're on site for the door and pool-alarm safety inspection required on every new pool.

You're present for the safety inspection
Pentair heat pump, heater, control panel and chemical controller on a finished pad
Pentair heat pump, heater, control panel and chemical controller on a finished pad
Heat pump, pumps and valve manifold set on the equipment pad
Heat pump, pumps and valve manifold set on the equipment pad
Filter, pumps and heat pump plumbed on the pad before the lines are painted
Filter, pumps and heat pump plumbed on the pad before the lines are painted
Weeks 10–12

Plaster & first swim

Plaster goes on, the final inspection clears, and the pool is yours. Fill it, balance it, and dive in.

Fresh interior finish with blue waterline tile as the pool starts to fill
Fresh interior finish with blue waterline tile as the pool starts to fill
Finished geometric pool and spa, filled, with sheer descents running
Finished geometric pool and spa, filled, with sheer descents running
Warranty

Our written warranty.

Every pool comes with California Trademark Pools’ written warranty. The main terms:

Structural (the pool and spa shell)
10 years
Pool equipment (submersible and water-feature pumps: 30 days, by the maker; the pool cleaner: 1 year)
3 years
Stonescapes and other pebble interior material
Lifetime limited (material) · 1 year workmanship
Plaster and plaster-based interiors
3 years material · 1 year workmanship
Rebar bleed
2 years
Tile, decks and underground installation
1 year

Every warranty starts at start-up, the day your pool equipment is started up, and covers the original buyer only (it is not transferable). Every warranty is limited to defects in workmanship or materials only. The structural warranty covers the pool and spa shell; plumbing such as the main drain, skimmer and returns is not part of it. The full terms, with every limit and the care your pool needs, are in the written warranty you get with your estimate and at signing.

Raised square spa with stone veneer at the end of a rectangular pool